Define IAS 11 — Construction Contracts in detail?

Share using link:

Direct share:

Jul 7 at 14:0:45
Ashiq
Ashiq
11

1 Answer

1
IAS 11 Construction Contracts provides requirements on the allocation of contract revenue and contract costs to accounting periods in which construction work is performed. Contract revenues and expenses are recognised by reference to the stage of completion of contract activity where the outcome of the construction contract can be estimated reliably, otherwise revenue is recognised only to the extent of recoverable contract costs incurred.

The objective of IAS 11 is to prescribe the accounting treatment of revenue and costs associated with construction contracts.

What is a construction contract?
A construction contract is a contract specifically negotiated for the construction of an asset or a group of interrelated assets. [IAS 11.3]

Under IAS 11, if a contract covers two or more assets, the construction of each asset should be accounted for separately if (a) separate proposals were submitted for each asset, (b) portions of the contract relating to each asset were negotiated separately, and (c) costs and revenues of each asset can be measured. Otherwise, the contract should be accounted for in its entirety. [IAS 11.8]

Two or more contracts should be accounted for as a single contract if they were negotiated together and the work is interrelated. [IAS 11.9]

If a contract gives the customer an option to order one or more additional assets, construction of each additional asset should be accounted for as a separate contract if either (a) the additional asset differs significantly from the original asset(s) or (b) the price of the additional asset is separately negotiated. [IAS 11.10]

What is included in contract revenue and costs?
Contract revenue should include the amount agreed in the initial contract, plus revenue from alternations in the original contract work, plus claims and incentive payments that (a) are expected to be collected and (b) that can be measured reliably. [IAS 11.11]

Contract costs should include costs that relate directly to the specific contract, plus costs that are attributable to the contractor's general contracting activity to the extent that they can be reasonably allocated to the contract, plus such other costs that can be specifically charged to the customer under the terms of the contract. [IAS 11.16]